Operation and control of a current source converter series tapping of an LCC-HVDC link for integration of offshore wind power plants
Cita com:
hdl:2117/103500
Tipus de documentArticle
Data publicació2016-12
Condicions d'accésAccés obert
Llevat que s'hi indiqui el contrari, els
continguts d'aquesta obra estan subjectes a la llicència de Creative Commons
:
Reconeixement-NoComercial-SenseObraDerivada 3.0 Espanya
Abstract
This work presents a series tapping station for integrating Offshore Wind Power Plants (OWPP) into a (Line Commutated Converter High Voltage Direct Current) LCC-HVDC transmission system. The tapping station allows to integrate wind power resources without building a new HVDC link and it is based on a Current Source Converter (CSC). However, the CSC requires a minimum DC current to extract the power coming from the OWPP which may not be guaranteed depending on the power conditions of the HVDC corridor. For this reason, this paper proposes a coordinated operation and control of the CSC and the OWPP. A steady-state analysis is performed to determine the appropriate AC voltage level of the CSC. A power reduction algorithm is presented to limit power extraction during a reduction in the current of the HVDC transmission system and under loss of communications between the CSC and the OWPP. The proposed algorithm and the performance of the system are validated through simulation results.
CitacióSau, J., Eduardo Prieto-Araujo, Galceran-Arellano, S., Gomis-Bellmunt, O. Operation and control of a current source converter series tapping of an LCC-HVDC link for integration of offshore wind power plants. "Electric power systems research", Desembre 2016, vol. 141, p. 510-521.
ISSN0378-7796
Versió de l'editorhttp://www.sciencedirect.com/science/article/pii/S0378779616302747
Fitxers | Descripció | Mida | Format | Visualitza |
---|---|---|---|---|
Operation and c ... tapping of an LCC-HVDC.pdf | 2,058Mb | Visualitza/Obre |