dc.identifier.citationHsiau, Hsian Jong; Lin, Chun Wei R.. A fuzzy pert approach to evaluate plant construction project scheduling risk under uncertain resources capacity. "Journal of Industrial Engineering and Management", Juny 2009, vol. 2, núm. 1, p. 31-47.
dc.identifier.issn2013-0953
dc.identifier.urihttp://hdl.handle.net/2099/8217
dc.description.abstractA plant construction project always involves lots of activities. Precise information about the activities duration is unfortunately unavailable due to the uncertain resources capacity. The fuzzy program evaluation and review technique (PERT) has been widely applied to solve the fuzzy project scheduling problem. This paper presents an extended fuzzy PERT approach with four major improvement aspects to support the construction project scheduling management: 1) Evaluate operation fuzzy times based on available working volumes, resources quantity and fuzzy capacity of resources, 2) Adopting a maximal 􀀂 i 􀀁 levelcut method to compare the fuzzy precedent activities times to determine the reasonable earliest starting times of each activity, 3) Using fuzzy algebra method instead of fuzzy subtraction method to compute the fuzzy latest starting times and 4) Developing a project scheduling risk index (PSRI) to assist the decision maker to evaluate the project scheduling risk. Simulations experiments are conducted and demonstrated satisfactory results.
dc.format.extent17 p.
dc.language.isoeng
dc.publisherSchool of Industrial and Aeronautic Engineering of Terrassa (ETSEIAT). Universitat Politècnica de Catalunya (UPC)
dc.rightsAttribution-NonCommercial 3.0 Spain
dc.rights.urihttp://creativecommons.org/licenses/by-nc/3.0/es/
dc.subjectÀrees temàtiques de la UPC::Economia i organització d'empreses::Direcció d'operacions
dc.subject.lcshProduction scheduling.
dc.subject.lcshProject management.
dc.subject.lcshConstruction projects
dc.subject.lcshFuzzy PERT approach
dc.titleA fuzzy pert approach to evaluate plant construction project scheduling risk under uncertain resources capacity
dc.typeArticle
dc.subject.lemacGestió de projectes
dc.subject.lemacPERT (Anàlisi de xarxes)
dc.subject.lemacConstrucció -- Projectes
dc.identifier.dlB-28744-2008
dc.description.peerreviewedPeer Reviewed
dc.rights.accessOpen Access
local.citation.authorHsiau, Hsian Jong; Lin, Chun Wei R.
local.citation.publicationNameJournal of Industrial Engineering and Management
local.citation.volume2
local.citation.number1
local.citation.startingPage31
local.citation.endingPage47


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record

Attribution-NonCommercial 3.0 Spain
Except where otherwise noted, content on this work is licensed under a Creative Commons license : Attribution-NonCommercial 3.0 Spain