Genetic algorithm for project time-cost optimization in fuzzy environment

Carregant...
Miniatura
El pots comprar en digital a:
El pots comprar en paper a:

Projectes de recerca

Unitats organitzatives

Número de la revista

Títol de la revista

ISSN de la revista

Títol del volum

Col·laborador

Editor

Tribunal avaluador

Realitzat a/amb

Càtedra / Departament / Institut

Tipus de document

Article

Data publicació

Editor

School of Industrial and Aeronautic Engineering of Terrassa (ETSEIAT). Universitat Politècnica de Catalunya (UPC)

Part de

Condicions d'accés

Accés obert

item.page.rightslicense

Creative Commons
Aquesta obra està protegida pels drets de propietat intel·lectual i industrial corresponents. Llevat que s'hi indiqui el contrari, els seus continguts estan subjectes a la llicència de Creative Commons: Reconeixement-NoComercial 3.0 Espanya

Assignatures relacionades

Assignatures relacionades

Datasets relacionats

Datasets relacionats

Projecte CCD

Abstract

Purpose: The aim of this research is to develop a more realistic approach to solve project time-cost optimization problem under uncertain conditions, with fuzzy time periods.

Design/methodology/approach: Deterministic models for time-cost optimization are never efficient considering various uncertainty factors. To make such problems realistic, triangular fuzzy numbers and the concept of a-cut method in fuzzy logic theory are employed to model the problem. Because of NP-hard nature of the project scheduling problem, Genetic Algorithm (GA) has been used as a searching tool. Finally, Dev-C++ 4.9.9.2 has been used to code this solver.

Findings: The solution has been performed under different combinations of GA parameters and after result analysis optimum values of those parameters have been found for the best solution.

Research limitations/implications: For demonstration of the application of the developed algorithm, a project on new product (Pre-paid electric meter, a project under government finance) launching has been chosen as a real case. The algorithm is developed under some assumptions.

Practical implications: The proposed model leads decision makers to choose the desired solution under different risk levels.

Originality/value: Reports reveal that project optimization problems have never been solved under multiple uncertainty conditions. Here, the function has been optimized using Genetic Algorithm search technique, with varied level of risks and fuzzy time periods.

Descripció

Document relacionat

Citació

Haque, Khan Md. Ariful; Hasin, Md. Ahsan Akhtar. Genetic algorithm for project time-cost optimization in fuzzy environment. "Journal of Industrial Engineering and Management", Desembre 2012, vol. 5, núm. 2, p. 364-381.