Building a deep isolating wall by an existing rail tunnel

Carregant...
Miniatura
El pots comprar en digital a:
El pots comprar en paper a:

Projectes de recerca

Unitats organitzatives

Número de la revista

Títol de la revista

ISSN de la revista

Títol del volum

Cita com:

Col·laborador

Editor

Tribunal avaluador

Realitzat a/amb

Tipus de document

Article

Data publicació

Editor

Institution of Civil Engineers

Condicions d'accés

Accés obert

Llicència

Creative Commons
Aquesta obra està protegida pels drets de propietat intel·lectual i industrial corresponents. Llevat que s'hi indiqui el contrari, els seus continguts estan subjectes a la llicència de Creative Commons: Reconeixement-NoComercial-SenseObraDerivada 3.0 Espanya

Assignatures relacionades

Assignatures relacionades

Publicacions relacionades

Datasets relacionats

Datasets relacionats

Projecte CCD

Abstract

This paper describes the design, construction and early performance of a retaining structure close to a subway tunnel in Barcelona. The excavation, about 16 m deep, was carried out in 2001 during the construction of a new hospital, and involved a rectangular area with the longer side (170 m) almost parallel to the tunnel. The design had to fulfil two requirements: first, the influence of the excavation on the existing tunnel had to be minimised; and, second, the new hospital had to be isolated from vibrations from the subway owing to the high sensitivity of the medical instruments. In order to achieve this, the retaining wall was designed to be independent of the main building, and movements during the excavation stages had to be controlled. In addition, the use of subhorizontal anchors was not allowed by the metro administration, and therefore the wall comprised a line of T-shaped panels linked to shorter intermediate panels excavated using a hydromill. The stability of the wall and bending resistance were provided by the buttressing effect of the forward-facing T and the compression in the panels and anchoring force provided by post-tensioning anchors drilled into the underlying bedrock through ducts installed in the rear section of the T panels. The wall was designed using a beam–spring model with ground parameters derived from in situ tests, and the interaction between the excavation and the tunnel was modelled using a plane-strain finite element analysis imposing the wall displacements on the section. Monitoring of the wall and the tunnel confirmed that the influence of the work on the neighbouring tunnel was negligible.

Descripció

Persones/entitats

Document relacionat

Versió de

Citació

Molins, C.; Ledesma, A. Building a deep isolating wall by an existing rail tunnel. Proceedings of the Institution of Civil Engineers Geotechnical Engineering, 2006, vol. 159, july, no. 3, p. 219.