New computational experiences on the Hoist Scheduling Problem for cyclic manufacturing of different products.
Tipus de documentReport de recerca
Data publicació2007-01
Condicions d'accésAccés obert
Llevat que s'hi indiqui el contrari, els
continguts d'aquesta obra estan subjectes a la llicència de Creative Commons
:
Reconeixement-NoComercial-SenseObraDerivada 2.5 Espanya
Abstract
Jobs of two products must receive the same treatments in a production
line of tanks. If the size of both batches is equal, we propose a cyclic manufacturing
composed of a job from batch 1 and a job from batch 2. A hoist ensures the transfer of
the jobs between tanks. The problem consists in the scheduling of hoist movements,
which is known as HSP (Hoist Scheduling Problem). There is a comparison between
completely separated and mixed production for both batches. The objective is to
determine a sequence which minimises the cycle time for two jobs from different
products (2-product cycle). We propose a branch-and-bound procedure, which can also
be applied to the 2-cycle case for a single product. The model can be extended to ncycles.