n-Cyclic Hoist Scheduling Problem to manufacture more than 2 products
Visualitza/Obre
Tipus de documentReport de recerca
Data publicació2012-07-27
Condicions d'accésAccés obert
Llevat que s'hi indiqui el contrari, els
continguts d'aquesta obra estan subjectes a la llicència de Creative Commons
:
Reconeixement-NoComercial-SenseObraDerivada 3.0 Espanya
Abstract
Jobs of more than two products (n>2) must be manufactured in a
production line of tanks. A hoist transports the jobs between tanks. If the size of both
batches is equal and the number of jobs is high, a cyclic scheduling can be proposed.
The problem consists in the scheduling of hoist movements, which is known as CHSP
(Cyclic Hoist Scheduling Problem). The objective is double: first, determine a sequence
of the n products in a job cycle and then minimise the cycle time for the given sequence
of products (n-cycle). We propose the use of a branch-and-bound procedure previously
developed, which was developed for the 2-cycle. As there are different sequences of
products, the experience demonstrates that the use of upper bounds as a result of
previous steps in the algorithms generally leads to the optimum solution in lower times.
CitacióMateo, M.; Companys, R. "n-Cyclic Hoist Scheduling Problem to manufacture more than 2 products". 2012.