Optimum short-term hydrothermal scheduling with spinning reserve through network flows
Cita com:
hdl:2117/15738
Tipus de documentArticle
Data publicació1995-08
Condicions d'accésAccés obert
Llevat que s'hi indiqui el contrari, els
continguts d'aquesta obra estan subjectes a la llicència de Creative Commons
:
Reconeixement-NoComercial-SenseObraDerivada 3.0 Espanya
Abstract
Optimizing the thermal production of electricity in the short term in an integrated power system when a thermal unit commitment has been decided means coordinating hydro and thermal generation in order to obtain the minimum thermal generation costs over the time period under study. Fundamental constraints to be satisfied are the covering of each hourly load and satisfaction of spinning reserve requirements and transmission capacity limits. A nonlinear network flow model with linear side constraints with no decomposition into hydro and thermal subproblems was usedto solve and thermal scheduling. Hydrogeneration is linearized with respect to network variables and novel thermal generation and transmission network is introduced. Computational results are reported.
CitacióHeredia, F.-Javier; Nabona, N. Optimum short-term hydrothermal scheduling with spinning reserve through network flows. "IEEE transactions on power systems", Agost 1995, vol. 10, núm. 3, p. 1642-1651.
ISSN0885-8950
Versió de l'editorhttp://ieeexplore.ieee.org/stamp/stamp.jsp?tp=&arnumber=466476
Fitxers | Descripció | Mida | Format | Visualitza |
---|---|---|---|---|
HerediaNabona_I3ETPS_95.pdf | Article publicat al la revista IEEE Transactions on POwer Systems | 1022,Kb | Visualitza/Obre |